May - July 201307/31/2013 Suburban Branch Construction of the reinforced concrete pipe on site “Reconstruction of the auto road “Rybnaya Sloboda – Yanchikovo” in Rybno-Slobodsky district of the Republic of Tatarstan. 07/31/2013 Sabinsky Branch Construction of the asphalt surface course on site “Reconstruction of the auto road “Timershik – Bolshoy Shinar”, km 4+200 – km 11+200, in Sabinsky district of the Republic of Tatarstan. 07/30/2013
Construction of the macadam road bed and asphalt bedding course on site “Construction of the auto road “Buraly – Rantamak” – Aleksandrovka” – Almetievsk – Musliumovo” – Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan. 07/28/2013 Mamadyshsky Branch Construction of the auto road “Ishkeyevo – Taveli – Chaksy”. The construction of double-course asphalt pavement layers here is finished. Slopes and road sides are being filled in and easement areas are being re-cultivated. 07/25/2013 Apastovsky Branch Reconstruction of the auto road “Kazan-Uliyanovsk” – Kamskoye Ustie” – Varvarino, km 0+000 – km 3+000 in Kamsko-Ustiynsky district of the Republic of Tatarstan is finished. 07/25/2013 Apastovsky Branch Reconstruction of the auto road “Sobolevskoye – Chulpanikha” in Verkhne-Uslonsky district of the Republic of Tatarstan is finished. 07/24/2013 Menzelinsky Branch The part of the auto road “Musliumovo – Saklov Bash – Yultimirovo”, km 1+600 – km 5+800 in Musliumovsky district of the Republic of Tatarstan is put into operation after reconstruction. 07/22/2013 Аrsky Branch Laying of the asphalt surface course on site “Constuction of the auto road Nizhnyaya Korsa – Verkhnyaya Korsa in Arsky district of the Republic of Tatarstan”. 07/19/2013 Menzelinsky Branch Auto road “Musliumovo – Saklov Bash – Yultimirovo”, km 1+600 – km 5+800 in Musliumovsky district of the Republic of Tatarstan 4.2 km long is being prepared for commissioning. 07/17/2013 Aksubaevsky Branch Macadam road bed and asphalt bedding course above it are being constructed on the auto road “Chistopol-Aksubayevo-Nurlat”-Chuvashskoye Yenoruskino in Aksubayevsky district of the republic. 07/17/2013 Aksubaevsky Branch Auto road “Aksubayevo-Yemel’kino”-Russkaya Kiremet’ in Aksubayevsky district of the Republic of Tatarstan. Here, asphalt wearing course was already laid and soft verges were padded. Pipe protecting works are going on. 07/17/2013 Menzelinsky Branch Earth roadbed is being constructed on the auto road on site “M-7 – Volga” – Novyi Mel’ken” in Menzelinsky district of the Republic of Tatarstan. 07/16/2013 Aksubaevsky Branch On photo: Auto road “Chistopol-Aksubayevo-Nurlat”-Chuvashskoye Yenoruskino”-Ilyashkino in Aksubayevsky district of the Republic of Tatarstan. Synthetic non-woven fabric “Dornit-2” is being laid on km 9+000 – km 12+20, sand-and-gravel mix bedding course is being constructed. Protective works on ferroconcrete culvert d 2x2 m on km 20+95 are finished. 07/16/2013 Mamadyshsky Branch Protective works on I/O pads of the pipes are being finished. Macadam roadbed is being constructed; asphalt bottom and surface course are being laid on auto road “Ishkeevo – Nizhniy Takanysh – Chaksy” in Mamadyshsky district of the Republic of Tatarstan. 07/16/2013
Sand subsoil and macadam roadbed are being constructed and geogrid is being laid on site “Construction of the auto road “Buraly Rantamak” – Aleksandrovka – Al’metyevsk – Musliumovo” – Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan. 07/15/2013 Menzelinsky Branch Subsoil is being constructed on site “Reconstruction of the auto road Tiukovo-Tatarskiye Yamaly, part km 17+550 – 21+000 in Aktanyshsky district of the Republic of Tatarstan”. 07/13/2013 Sabinsky Branch Laying out the grade and slopes of the embankment on site “Reconstruction of the auto road Timershik – Bol’shoy Shinar, km 0+000 – km 1+371; km 4+200 – km 11+200 in Sabinsky district of the Republic of Tatarstan”. 07/12/2013 Apastovsky Branch On photo: Construction of the road bed using cold regeneration method with addition of bonding on site “Bypass of settlement Bolshiye Kaibitsy” in Kaibitsky district of the Republic of Tatarstan. 07/12/2013
Asphalt bottom course is being finished on auto road Staroye Drozhzhanoye – Karakityan km 7+800 – km 1+056. 07/11/2013 Suburban Branch Macadam roadbed is being constructed and geogrid is being laid on site “Reconstruction of the auto road “Kazan-Orenburg” – Rybnaya Sloboda – Kornoukhovo” – Bolshoy Oshnyak – Malyi Oshnyak” in Rybno-Slobodsky district of the Republic of Tatarstan. 07/11/2013 Suburban Branch Construction of the earth roadbed is being finished; subsoil is being spread and geogrid is being laid on site “Reconstruction of the auto road “M-7 “Volga” – Pervoye Maya – Kamysh in Pestrechinsky district of the Republic of Tatarstan. 07/11/2013
On photo: Public road maintenance: grass mowing on roadsides and slopes, patching repair using jet injection method with БЦМ machines, cracks rehabilitation. 07/07/2013 Nizhnekamsky Branch Ground works are going on, subsoil and macadam road bed are being constructed on the auto road “Menzelinsk-Russkiy Karan-Togashevo-Kuzembetyevo”-Yamakovo in Menzelinsky district of the Republic of Tatarstan. 07/05/2013 Аrsky Branch Base course of the driveway of asphalt-concrete is being laid after scraping on the auto road “Kazan-Malmyzh” in Baltasinsky district of the Republic of Tatarstan. 07/05/2013 Аrsky Branch Ground works are going on and subsoil is being constructed on site “Reconstruction of the auto road Arsk-Bolshaya Atnya km 27+600 – km 29+000 in Atninsky district of the Republic of Tatarstan. 07/05/2013 Mamadyshsky Branch Construction of engineering structures and earth roadbed is being finished on auto road Ishkeevo-Nizhniy Takanysh-Chaksy. 07/04/2013 Menzelinsky Branch On photo: Ceremony of commissioning of the auto road “Aktanysh-Poisevo”-Kuziyakino” 6.0 km long in Aktanyshsky district of the Republic of Tatarstan. 07/04/2013 Menzelinsky Branch On photo: Site “Musliumovo – Saklov Bash – Yultimirovo” in Musliumovsky district of the Republic of Tatarstan”. Construction of asphalt-concrete wearing course 4.2 km long is finished, and strengthening of the slopes and channel of water conduit pipe is going on. 07/04/2013 Mamadyshsky Branch Construction of asphalt-concrete wearing course is finished on the auto road M-7 “Volga”-Urazbakhtino. 07/04/2013 Menzelinsky Branch Auto road earth bed is being constructed on site “Reconstruction of the auto road Tiukovo-Tatrskiye Yamaly, part km 17+550 – 21+000 in Aktanyshsky district of the Republic of Tatarstan”. 07/04/2013 Nizhnekamsky Branch Auto road earth bed is being constructed on the auto road “Menzelinsk-Russkiy Karan-Togashevo-Kuzembetyevo”, part Kuzembetyevo-Kadryakovo. 07/04/2013 Aksubaevsky Branch On photo: Auto road “Aksubayevo-Yemel’kino”- Russkaya Kiremet’ in Aksubayevsky district of the Republic of Tatarstan – construction of the road mat, foundation for water pipe conduit and asphalt covering. 06/22/2013
The road bed is being constructed on the auto road Staroye Drozhzhanoye – Karakityan using “mix-in-place” method (Gravel-sand + bonding). 06/22/2013
Roadbed side cutting is being planned on site Reconstruction of the road “Tsivilsk-Uliyanovsk”-Khornovar-Shigali, km 0+014 – km 5+207 in Drozhzhanovsky district of the Republic of Tatarstan. 06/21/2013 Аrsky Branch Construction of the bottom layer is going on on site “Construction of the auto road Nizhnyuaya Korsa – Verkhnyaya Korsa in Arsky district of the Republic of Tatarstan”. 06/21/2013 Suburban Branch On photo: Reconstruction of Tatarstan Street in Kazan - construction of the racking course. 06/21/2013 Suburban Branch On photo: Reconstruction of Fuchika Street in Kazan - construction of the surface course. 06/18/2013 Aksubaevsky Branch Site: “Construction of the auto road “Chistopol’ -Aksubayevo-Nurlat”- Chuvashskoye Yenoruskino”- Ilyashkino in Aksubayevsky district of the Republic of Tatarstan”. Construction of the road bed is going on. The steel concrete water 2x2 m pipe conduit was mounted, now the joints are being sealed. Protective works are started. 06/17/2013 Menzelinsky Branch Construction of macadam roadbed on site “Reconstruction of the auto road Drive to settlement Barsukovo in Aktanyshsky district of the Republic of Tatarstan”. 06/16/2013 Suburban Branch Milling, leveling and macadam and mastic asphalt concrete courses construction and installation of guard rails on drive to international airport of Kazan. 06/15/2013 Aksubaevsky Branch Construction of the road bed on the auto road “Chistopol’ -Aksubayevo-Nurlat”- Chuvashskoye Yenoruskino”. Sand and gravel bedding course and M-400 macadam road bed are being made here. Installation of headwalls and sections of the steel concrete water Ø1.5 m pipe conduit is finished and waterproofing works are started. 06/14/2013 Menzelinsky Branch Roadside soil stabilization on the auto road “Aktanysh – Poisevo – Kuziyakino” in Aktanyshsky district of the Republic of Tatarstan”. 06/13/2013 Menzelinsky Branch ЩМА-15 macadam and mastics asphalt concrete carpet coat is being made on the auto road “Musliumovo – Saklov Bash – Yultimirovo” in Musliumovsky district of the Republic of Tatarstan”. 06/13/2013
On photo: Road surface regeneration works (first trip of the recycler) on the auto road Staroye Drozhzhanoye – Karakityan km 7+800 – km 16+056 in Drozhzhanovsky district of the Republic of Tatarstan. 06/11/2013 Mamadyshsky Branch The works on site “Mamadysh-Tiuliyach-Vasil’yevo” are finished. Ground works are being executed on sites “Ishkeyevo-Nizhniy Takanysh-Chaksy” and “Usali-Albayevo-Vladimirovo”. 06/05/2013 Apastovsky Branch Earth roadbed is being stabilized with lime on site “Normalization of road network in village Dolgaya Polyana”. 06/04/2013 Аrsky Branch Ground works are being executed on site “Constuction of the road Nizhnyaya Korsa – Verkhnyaya Korsa in Arsky district of the Republic of Tatarstan”. 06/01/2013 Menzelinsky Branch Site: Construction of the auto road “Almetyevsk – Musliumovo – Igenche” in Musliumovsky district of the republic. Ground bed of the auto road is being made here. 06/01/2013 Apastovsky Branch On photo: Construction of the road bed on the auto road “Kazan-Uliyanovsk”-Staroye Baryshevo-kamskoye Ustiye-Yasashno-Baryshevo. 06/01/2013 Apastovsky Branch Cold regeneration method is being used to construct road bed on the auto road “Ulanovo-Karatun”- B. Kaybitsy, km 0+150 – km 8+300. 06/01/2013 Menzelinsky Branch On photo: Site “Aktanysh-Poisevo”-Kuziyakino” in Aktanyshsky district of the Republic of Tatarstan. Asphalt-concrete surface course is being laid here. 06/01/2013 Menzelinsky Branch Site: Reconstruction of the auto road Drive to settlement Barsukovo in Aktanyshsky district of the Republic of Tatarstan. On photo: Construction of the road bed of the auto road. 06/01/2013
Construction of the auto road “M-7 Volga”- Kutlu Bukash – Rybnaya Sloboda – Bikchurayevo” in Rybno-Slobodsky district of the Republic of Tatarstan is going on. 05/18/2013 Sabinsky Branch Laying of the asphaltic mastic macadam (ЩМА-15) carpet coat on site “Reconstruction of the auto road “Sardek Bash – Lel’vidj – settlement Chura” on part km 0+000 – km 4+250 in Kukmorsky district of the Republic of Tatarstan. 05/18/2013 Mamadyshsky Branch The earth roadbed is finished and the bottoming and macadam foundation are being finished on the auto road “Mamadysh-Tiuliyachi-Vasil’yevo”. 05/13/2013 Suburban Branch On photo : Ground works on site “Kazan-Orenburg-Rybnaya Sloboda-Kornoukhovo-Bolshoy Oshnyak-Maliy Oshnyak”. 05/07/2013 Nizhnekamsky Branch Scraping works are finished on Zakiyev str. in Kazan. 05/02/2013 Suburban Branch On Pushkin str. in Kazan the workers of the branch are scraping the road and laying the racking course. |